Highway BR-101/SC – Paulo Lopes to São João do Sul

Highway BR-101/SC – Paulo Lopes to São João do Sul 

Home > Projects > Highway BR-101/SC – Paulo Lopes to São João do Sul

Project's progress

Studies

Public Consultation

TCU Assessment

Bidding Documents

Auction

Contract

09/21/2018
05/10/2019
09/23/2019
11/07/2019
02/21/2020
07/06/2020
  • Completed
  • In progress
  • To be performed
  • CLASSIFICATION BY MEETING

    2nd Meeting

  • SECTOR

    Highway

  • ASSET

    Brownfield Project

  • PROJECT STATUS

    Completed

  • TYPE OF PARTNERSHIP

    Common Concession

  • UF

    SC

  • CAPACITY

    220,42 km

  • INVESTMENT CAPEX

    2,900,000,000.00

  • INVESTMENT OPEX

    3,600,000,000.00

  • MAJOR AGENCIES INVOLVED

    ANTT, Minfra e EPL

  • TERM (YEARS)

    30 anos

  • AWARD CRITERIA

    Lowest tariff rates

Project Summary

Concession of a stretch of BR-101 Highway with a length of 211 km in the State of Santa Catarina

The BR-101/SC Highway Project was qualified in the Investment Partnerships Program (PPI) at the 2nd Meeting of the PPI Council held on March 7, 2017. The concession, which will be for 30 years, includes the stretch of highway connecting the municipalities of Paulo Lopes and São João do Sul, both in the state of Santa Catarina, with a length of 220.42 km and average annual traffic of 24,000 vehicles a day.

The feasibility study was presented, via the Manifestation of Interest Procedure (PMI), in May 2016. The analyses, currently under review by the Brazilian Enterprise for Planning and Logistics (EPL), demonstrate the need for investments to increase infrastructure capacity, maintenance and provide operating services.

The investments are of R$ 4.1 billion in CAPEX and another R$ 4.5 billion in OPEX. The concession foresees the improvement in performance standards and the implementation of works that increase capacity, with special emphasis to:

• 32 pedestrian walkways;
• 74 km of marginal roads;
• 25 bus turnouts;
• 22 km of capacity expansion (3rd lane);
• 185 adjustments of acceleration and deceleration lanes;
• 222 eliminations of frontal conflicts;
• 46 movement channels on the marginal lanes;
• 29 improvements to side accesses; and
• 44 implementation of traffic circles

The works to be carried out will allow the increase of capacity and the improvement of the level of service in the roads, providing a reduced number of accidents and traffic jams. 

Importance: Works will enable capacity expansion and a better level of service, providing a reduction of accidents and congestion, improvement in trafficability, as well as a significant contribution to the economic development of the region.

  • Project Current Situation

    Final phase of studies elaboration.

Gallery

Stretch of the Highway BR-101/SC under study

Stretch of the Highway BR-101/SC under study