Agrovia Terminal in the Port of SUAPE/PE

Agrovia Terminal in the Port of SUAPE/PE 

Home > Projects > Agrovia Terminal in the Port of SUAPE/PE

Project's progress

Investment Plan

EVTEA

Contract amendment

05/16/2018
Não definido
  • Completed
  • In progress
  • To be performed
  • CLASSIFICATION BY MEETING

    3rd Meeting

  • SECTOR

    Ports

  • ASSET

    Brownfield Project

  • PROJECT STATUS

    Extension

  • TYPE OF PARTNERSHIP

    Authorization for New Investments

  • UF

    PE

  • CAPACITY

    59 mil toneladas / ano (estimativa)

  • BASE DATE

    08/2017

  • INVESTMENT CAPEX

    129,341,354.00

  • MAJOR AGENCIES INVOLVED

    MTPA e ANTAQ

  • TERM (YEARS)

    25 anos

Project Summary

It is an existing terminal with 72,542 m², initially tendered for exclusive handling of sugar.
The project refers to the authorization to handle new types of cargo (vegetable solid bulks), through investments.

In general terms, the project contemplates 3 implementation stages with investments of BRL 170 million, of which BRL 95 million are related to equipment and BRL 75 million are related to buildings, which aim to provide the Terminal with the capacity to handle other vegetable bulks. Therefore, the Terminal will have the capacity for 29,000 tons per year of bagged sugar and 30,000 tons per year for other vegetable solid bulks (wheat, malt or rice).

Gallery

Agrovia Terminal in the Port of SUAPE/PE

Agrovia Terminal in the Port of SUAPE/PE

Other projects

  • CPRM MINING RIGHTS - Calcário de Aveiro / PA

    Veja Projeto
  • New Municipal Hospital for Children and Adolescents in Guarulhos-SP (NHMCA)

    Veja Projeto
Acesso à Informação
Governo do Brasil